Page 1 of 2    Previous    Next
Project implementation progress in April 2012.
Project implementation progress in April 2012.

Project implementation progress in March 2012.
Project implementation progress in March 2012.

Project implementation progress in February 2012.
Project implementation progress in February 2012.

Project implementation progress in January 2012.
Project implementation progress in January 2012.

Project implementation progress in December 2011
Project implementation progress in December 2011

Project implementation progress in November 2011
By the end of November 2011, Vinaconex-ITC is implementing the following items of the project

Project implementation progress in October 2011
Project implementation progress in October 2011

Project implementation progress in 3 rd and 4th weeks, September 2011
Project implementation progress in 3 rd and 4th  weeks, September 2011

Project implementation progress in 1st and 2nd weeks, September 2011
Project implementation progress in 1st and 2nd  weeks, September 2011

Project implementation progress in August 2011
Project implementation progress in August 2011

Project implementation progress in 3rd and 4th weeks, July 2011
Project implementation progress in 3rd and 4th weeks, July 2011

Project implementation progress in 1st and 2nd weeks, July 2011
In July, Vinaconex-ITC continue to implement and speed up the implementation of the following bid packages
Project implementation progress in 3rd and 4th weeks, June 2011
AT this moment, Vinaconex-ITC has finalized river embankments of IIA and IIB phases;
Project implementation progress in 2nd week of June 2011
In the 2nd week of June, Vinaconex-ITC has completed and utilized flooding tank, hand-rail for roundabout (which belongs to the landscape for Tung Thu Beach).
Project implementation progress in 1st week of June, 2011.
Now, Vinaconex-ITC has completing some items of phase I and urgently  accelerate items of phase II.In June. 2011, expected complete items to process weak soil base, paved sidewalks, plant trees of phase IB.